8/19/2024 12:39 p.m. Update: This project will now begin on Monday, August 26. Thank you for your patience and understanding. The original article has been updated to reflect the change.
The Water Resources Construction Division will be replacing sanitary sewer mains beginning Monday, August 26, in the street right-of-way on the following streets:
-
Cemetery St. from Bickett St. to Parker St.
-
Magnolia St. from Crescent St. to Griffith Rd.
-
Branch St. from Sycamore to Lancaster Ave.
-
Efird St. from Sanford St. to College St.
This project will take approximately six weeks to complete, weather permitting.
Temporary road closures will be necessary within the project limits, so please consider alternate routes. Emergency service vehicle access will be provided at all times. Normal collection of garbage and residential/commercial deliveries will be provided access.
All damaged/disturbed items will be restored or replaced at the end of the project. We apologize in advance for any inconvenience experienced during construction.